8 July 2021

Base building works

  • Structure poured up to Level 7.
  • Formwork stripped across all levels.
  • Lower ground to ground floor walls and service rough in
    complete, sheeting commenced.
  • Level 4 core amenities framing commenced.
  • Façade installation has begun on Level 4.

Fitout works

  • Off site works only at this stage.
  • Audio Booth batches complete and delivered to Sydney.
  • Audio booth installation scheduled for July 2021.
  • FF&E fabrication ongoing.
  • Workstations fabrication ongoing.
  • Architectural 100% design presentation delivered 15
    June 2021.
  • Services 100% design presentation to be delivered
    during week commencing 26 July 2021.
  • Level 7 performance