SITE PROGRESS UPDATE: 8TH OF JULY 2021

Base building works

  • Structure poured up to Level 7.
  • Formwork stripped across all levels.
  • Lower ground to ground floor walls and service rough in
    complete, sheeting commenced.
  • Level 4 core amenities framing commenced.
  • Façade installation has begun on Level 4.

Fitout works

  • Off site works only at this stage.
  • Audio Booth batches complete and delivered to Sydney.
  • Audio booth installation scheduled for July 2021.
  • FF&E fabrication ongoing.
  • Workstations fabrication ongoing.
  • Architectural 100% design presentation delivered 15
    June 2021.
  • Services 100% design presentation to be delivered
    during week commencing 26 July 2021.
  • Level 7 performance

SITE PROGRESS UPDATE: 2ND OF JULY 2021

SITE PROGRESS UPDATE: 18TH OF JUNE 2021

* Building samples.

SITE PROGRESS UPDATE: 19TH OF MAY 2021

SITE PROGRESS UPDATE: 8TH OF APRIL 2021

SITE PROGRESS UPDATE: 9TH OF MARCH 2021

A few new snapshots from Westmead. The process for imagining MARCS Institute for Brain, Behaviour & Development, THRI and our many collaborators from Western and beyond working together in new spaces at Westmead started back in 2018. It’s taking shape! The development through Western Growth includes CSIRO eHealth and Biosecurity as research neighbours. Still some work ahead! Thank you OEC, THRI, MARCS and so many schools and divisions contributing to visioning, designs and realisation.